D&M Earthmoving of Plymouth, Illinois, was awarded a fixed-price contract for
$4,151,975 to construct a series of flood control levees and support structures. The
contract was to be completed in 800 calendar days with 435 days allowed for adverse
weather conditions and 365 days for construction. During the project, 9 major floods
occurred totaling 631 days of flooding. The final contract duration was 1747 calendar
days.
CECA prepared a series of requests for equitable adjustment (claims) in order for the
contractor to recover the additional costs incurred.
D&M was compensated for the amount of additional work and extended jobsite overhead
costs.
|